The Pearl Qatar -Viva Bahriya hand over.
Hello,
I have a question for some of you. We received our letter of hand over stating that the snagging will be on Jan (???) 2011 and the hand over on Jan. (?)2011. I don't want to give the exact dates. We cancelled our contract were we are living and getting the moving company today. However a friend told us yesterday, Dec.20th that:
"After completion of the Construction, there will be testing & commissioning, which may take another 3-4 months !!." Meaning, we wouldn't be able to move in.
I know I should talk to UDC and I will, but I want to know if this is possible. We will be in big trouble if this really happens.
If someone could confirm this for me, that would be great. Can you imagine on the (???of January) without a place were to go?... Ouch!!!.
...
Which building exactly you are talking about? Viva Bahriya has 29 buildings.
well if they said hand over keys and ready to move in...
But still I would be careful as you might have frequent interruption in services like water and so on. Facilities under repair and not function.
out of experience if commissioning and snagging is done with no occupants it can be done in 3-5 months. However if occupied it can drag over years and some might never be done.
It is possible, you did not understand what they told you in the letter.
hand over
did they mention hand over to you?
sure it is hand over from contractor to management company
of course there is snagging, testing and commissioning and this will take its time.
did they tell you ready to hand over the keys to you and move in?