Qatar Rail ‘reviewing’ project in West Bay
Qatar is building from scratch a metro system and larger national rail network, including freight and long-distance passenger lines that must largely be completed when it hosts the 2022 soccer World Cup
Qatar has delayed a $3bn underground rail line planned as part of a multibillion-dollar infrastructure upgrade in the state after designs showed the project would run over-budget, several people familiar with the matter said.
Qatar Railways Company, the operator of the planned QR130bn ($36bn) rail network, in early September decided to rethink the design of the West Bay Automatic People Mover due to cost and the complexity of building a 11km, underground rail line through the heart of Doha’s glitzy new financial district, contractors and two people familiar with the matter told Zawya Dow Jones.
All tenders on the West Bay project have been cancelled until Qatar Rail concludes a feasibility study into its options.
“Unfortunately Qatar Rail announced that the project is frozen,” said Mickey Raviv, director of marketing and business development at Bombardier’s transport division, which bid for the rail system.
The other bidders were Siemens AG, Japan’s Mitsubishi Heavy Industries Ltd and a consortium made up of Marubeni Corporation and KobelCo.
Raviv said Qatar Railways had told Bombardier that it would retender the contract once it had assessed its options.
Qatar is building from scratch a metro system and larger national rail network, including freight and long-distance passenger lines that must largely be completed when it hosts the 2022 soccer World Cup. The state has plans to spend some $150bn on domestic infrastructure over the next five years, which has attracted huge interest from local and international companies alike.
Qatar’s review of the West Bay project comes at a time when other Gulf states are also reconsidering some of their spending plans amid concerns over the economic outlook in the US and Europe, slowing growth in Asia and falling income from lower crude oil prices.
Qatar said last week economic growth may only reach 5% in 2012, down from 15% this year.
“With expensive, major works looming on the horizon for the 2022 World Cup, it is unsurprising to see some projects in Qatar slowing down,” said David Roberts, deputy director at Doha-based Royal United Services Institute for Defence and Security Studies.
“This is an expensive rail system for a very small part of Doha -- it was always likely to be a challenging project.”
The West Bay system is set to feed into the Doha Metro and was originally due for completion in 2018, with construction slated to start in early 2012. Deutsche Bahn did the masterplan, supervision and design on the scheme, while Lea + Elliott conducted preliminary engineering.
Qatar Railways is now considering a variety of options for the West Bay project, including taking the lines above ground to street level.
“They think this will be cheaper and less complex,” said one person familiar with the matter.
Another person familiar with the matter said the start date for construction could be pushed back by around 18 months.
Gulf-Times.com
but they must see why the cost is high. It's highly likely here that profit margins are kept extremly high. And how can they bring profit margins of supplier to lower side?
So Qatar Railway will look EXACTLY like the Dubai Metro?? (according to these photos) Not a bad thing of course!
@kts1969, the Dubai Metro has a whole mix of people using it on a daily from all levels of society. Frankly, if the service is good enough I know loads of people who will jump on a metro to work if it's convenient, rather than face the dangerous roads of Doha!
The underground WILL NOT work in West Bay. None of the existing buildings were built with this in mind, and not forgetting, this is all reclaimed land! More time and cost effective to go above ground.
There will be a lot of painful traffic times ahead, but I for one can't wait to see what they do.
And why would we have mass transit in the swanky financial district . Most of the blokes in that area would anyway have their own Jags and Mercs- doubtful whether they would part with it . Why not run the rail directly into Lulu Hypermarket? It would then become real mass transit
Underground is the way to go because if you go above ground level it could ruin the buildings near it's path but Qatar doesn't really have a public transportation system in a sense it could be abandoned after use for 2022 so the cost over sustainability would be too hard to weigh.
Good to see the Rail-hostesses!
An one got a clue if the underground project going on at the corniche was for the railways or for a highway? I assume it was supposed to connect NDIA to west bay
urbanism error
WILL BE HELL OF TRAFFIC IN 2 YEARS...........GOVT SHOULD NOT SHIFT CONSTRUCTION OF NEW BUILDING TO NEW AREAS UNLIKE WEST BAY...
QP HQ IS GOT 11 OFFICE BUILDINGS BUT WHEN IT FINSH THAN WE CAN SEE WHAT WILL HAPPEN IN WEST BAY!!!
to hell with taco bell.....
yippe now i can dream of taco bell at the subway stations
....