Dear all QL Friends before doing anything if we think twice it will be better for all , I am not against to help worker we all are trying to do from the humanitarian ground but Qatar is a country where we can’t help from our bottom of heart , we can see the worker waiting for their sponsor/company more then 3 / 4 days in Doha airport , we see thousands of abandoned worker searching legally identification , we see thousands of worker not getting salary since more then 6 month, we see thousands of workers not fulfilling basic needs by company ( Resident permit on time ,water, electricity, healthcare )
I urge all QL friend this coming Thursday is Labor day ( may 1st ) why not we celebrate labor day some where and collect stuff and invite most of company needy labor and hand over to them all stuff , again I am not against to help HBK worker , I have also lot of stuff I can come with , meanwhile what are these Org doing ? Red cross societies , Qatar charity ( most of hospital, supermarket, hotel and other public place you will see their presentation to collect huge money)
Sorry for if any convenient its just my personnel opinion ..Happy Labor day !!!!
…………
HBK is company of Sheikh Hamad Bin Khalid Al Thani,
HBK annual turnover of the Group is around QR. 250 million (USD. 70 Million) and the turnover planned for the year 2007-2008 is around QR. 700 million (USD. 191 Million). Just think once if they spend only 1% of their turn over for their worker how much it will be ? and another hand make sure any gift or charity they will accept or not ? its not Tsunami for them , just accident
http://contracting.hbkholding.com
http://www.hbkholding.com/companies.htm

The annual turnover of the Group is around QR. 250 million (USD. 70 Million) and the turnover planned for the year 2007-2008 is around QR. 700 million (USD. 191 Million).

H.B.K. Power Cleaning W.L.L is a specialist Company in the application of corrosion protection products to the surfaces of buildings and industrial plants. The Company was found in 1973 and owned by Sheikh Hamad Bin Khalid Al Thani in association with Messrs Power Cleaning Ltd. of U.K.
16 Feb 2008 Contract Signing Ceremony of Ras Laffan 'C' Water Transmission Pipelines - GTC 158/2007
Design, Supply & Construction of 82Km of Water Transmission DI Pipeline of dia ranging from DN 1600mm to DN 600mm connecting Ras Laffan to Duhail. Also, the project involves Construction of associated valve chambers and supply, design and laying of Fiber Optic cable for whole length along the pipeline.
Awarded: February, 2008
Project Value: 881,505,000.00
02 July 2007-Doha & Rayyan Sewerage Construction of new PS 25 awarded to HBK
The Project comprised the Construction of a foul sewage pumping station (N25) of 3,300 It/sec capacity comprising twin wet wells, screening channels and pump chamber below ground and motor room, control room, offices, generator room and toilet facilities above ground.

The works also includes Construction of two 1200mm ductile iron rising mains from Pumping Station N25 along Markhiyah Street to a point adjacent to Arab League Street where a discharge chamber is to be constructed by others. The Works shall include construction of a surge vessel chamber
Awarded: July, 2007
Project Value: 187,500,000.00
30 July 2007-GTC 128/2006 Permanent Reservoir & PS for Shahaniya to Dukhan awarded to HBK
Awarded: July, 2007
Project Value: 139,092,741.00
09 September 2006 - Agriculture And Quarantine Buildings Project
Awarded: September, 2006
Project Value: 57,000,000.00
07 September 2006 -Truck Inspection & Clerance Area Project awarded to HBK
HBK Contracting Company has been awarded the Truck Inspection & Clearance Area Project at Abu Samra Customs Post. The Project comprises of Construction, Completion and Maintenance of Trucks Inspection Clearance Area at Abu Samra Custom Area covering a free area of 13,600 m2 with a total built up area of 5830m2 of buildings
Awarded: September, 2006
Project Value: 117,500,000.00
Contract Signing Ceremony of GTC 70/2005 Project
Water Supply to Madinat Al Shamal, Al Kaaban, Al Jerian and Urn Salal comprises laying of DI & HDPE pipes and fittings for water mains of dia ranging between 100mm to 600mm with approximate total length of 16o km and the associated pipework, as well as installation of MDPE pipes and fittings as Service Connections to the Customers and the associated pipework
Awarded: April, 2006
Project Value: 99,000,000.00
09 May 2006 HBK has awarded Al Asiri Tower Project
The Contract between HBK Contracting Co. W.L.L. and Qatar Islamic Bank (Client) for the Construction of Al Asiri Tower (2B+G+21) at West Bay has been signed on 09/05/2006. The duration of project is 24 months.
Awarded: May, 2006
Project Value: 95,000,000.00
29/10/2005 HBK has Awarded the Staff Accommodation at Abu Samra Customs Post
The works comprise the construction and maintenance of accommodation blocks for different grades of staff and associated ancillary and service buildings. The buildings are constructed of reinforced concrete. The external works are extensive and comprise roads, parking, paving, soft landscaping, irrigation, external sports courts and boundary wall including all external services.
Awarded: October, 2005
Project Value: 91,000,000.00